96 Air-conditioned Ensuite Cabins have been purchased, providing a new level of comfort and privacy for guests.
21 Aug Turf was laid this morning along the “Avenue.” Steps and landings are continuing for the others
3 August All the bedrooms are wired up but getting the power to the whole area has been hard. We got delayed ten days by underground obstacles. Similar with the water. Ten bedrooms have full water supply now, we start again on Monday. I think by Thursday we will have good results!
27 July – The last of the Cabins was hoisted onto the foundations at 11:08 this morning and is being welded down. The first bathroom became functional with all plumbing connected (but not electricity yet) at 2:00pm.
23 July – Big day today. Fourteen bunkhouses hoisted into position ready for electrics, plumbing and steps!
20 July – Five of the twenty-four buildings have been craned onto the foundation poles and plumbing and electricity connection started. We lost a week because of a crane shortage but we are back on track now.
6 July – Most of the trenches are now filled in. Next week the foundation poles go in, then the cabins are lifted in & welded into place.
25 June – Work is underway to have all the cabins sited & plumbed.
Thank you to Chris Hamerton for the photos / updates – and the hard work!